We successfully completed the works within the agreed 20-week contract period.
Key elements included
– Formation of new 400 space van park including installation of EV charging infrastructure
– Formation of new vehicular entrance and access road from adjoining public highway
– Formation of new service yards and staff parking areas
– Installation of new foul drainage infrastructure including pumping station and new rising main
– Installation of whole site surface water drainage infrastructure including separator tanks
– Surfacing and white lining
Key fact
– c. 11,000m3 excavation and bulk earthworks
– c. 7,000m3 imported sub-base material
– c. 20,000m2 surfacing
– Installation of c.1,100m of pre cast concrete ducting channels
– c. Construction of Legato block retaining structures
– Lime stabilisation